Golf course architects get to work in some exciting and unique locations. I get asked all the time which are my favorites, or which are the most challenging.
In the case of Anchorage Golf Course, both apply.
Having worked in some remote locations, including India and parts of Southeast Asia, it is interesting how a place like Alaska can feel so remote but also make you feel at home.
On every golf project, we try to maintain a certain level of quality control through our detailed drawings and specifications. But what happens when following the specifications becomes impractical? Exercising this flexibility can mean plunging into the unknown and being creative in how you achieve a quality golf product when what we usually consider a given becomes anything but.
Our work in Anchorage has taught us just that over the past few years. The challenge of preparing Anchorage Golf Course for the 2022 USGA Women’s Senior Amateur Championship required a non-traditional construction plan. That pressure, along with a shorter construction season, harsh environment, and selective windows throughout the year to execute the work meant we had to exercise patience, flexibility and creativity to get the job done at a high level. Looking back on our time working with Anchorage Golf Course so far got me thinking. What lessons can we take from this experience to ensure every project is successful? Below is what I would call a non-exhaustive list of lessons learned from Anchorage that might just help you with your upcoming project:
Know your constraints
Regardless of your scope of work, there is no substitute for a thorough site inventory and analysis process. In the case of Anchorage, knowing the climatic, physical and fiscal challenges well ahead of time allowed us to formulate a plan to work effectively within the constraints. However, maintaining flexibility in our approach allowed us to navigate unpredictable weather conditions, logistics and an ever-tightening tournament schedule.
Knowing we had to be ready for the tournament by a certain date drove the rest of the process. Factoring in extended — then reduced — daylight hours, weather history, growing schedule and current staffing needs allowed us to work backward from the tournament date to create a schedule with milestones that kept the work efforts on track.
Create your road map
Plan early and often. In all cases, the preliminary and master planning phases of a project make up the smallest percentage of a consultant’s fees but provide the best value. Building the proper framework for a project is one of the easiest and cheapest ways to set yourself up for success. For Anchorage, a detailed master plan allowed us to prioritize what work needed to occur ahead of the USGA tournament to ensure the most significant impact.
With the master plan as our guide, the team determined that bunkers would have the greatest impact not only on strategy and challenge, but also on how the course presented itself for tournament play.
Maintain quality control
The devil is in the details. The little things make or break a project. When a designer shows up and “does his thing” without providing details to help control costs, the owner loses. Having a detailed set of drawings to bid not only gives builders clear direction up front but also helps control the quality of the end product when the architect can’t be present every day. Unless you are prepared to house and feed your architect for the duration of the project, a detailed set of drawings is the best way to close the loop of the interpretation by a contractor while also providing a baseline to track the project’s budget.
Once we agreed on our goals and objectives for execution prior to the Senior Women’s Amateur, R|D created a working design sketchbook that included detailed drawings for every work area complete with grading, drainage and grass lines. This became the day-to-day reference for the client and construction staff who were present on the site every day. Complete with quantities and specifications, tracking and controlling the budget was streamlined, allowing for instant feedback and the ability to address any issues much more quickly.
Depend on trusted allies
Ensure that the architect can place a shaper they trust on the project. Shapers are the architect’s eyes and ears and the artist’s paintbrush. Shaper Jay Smith played an integral role in our success at Anchorage due to his talent and knowledge of golf course construction that he passed on to local laborers and staff to help get the job done. In Anchorage, placing an entire construction outfit on the project was cost prohibitive and impractical.
Having Jay there for us to lead the team paid dividends in the long run because our previous relationship on other projects instilled the trust that is needed between architect and shaper. Jay’s understanding of how we approach projects and his buy-in for the vision were the glue in bringing together the on-site team to execute.
Be willing to improvise
Specifications are gospel until they’re not. In today’s economic climate, the labor shortages and logistical problems with obtaining materials and equipment are exacerbated by the fact that a place like Anchorage is thousands of miles from everything. The likelihood of finding your Augusta National white sand for bunkers is a pipedream. Speaking of pipe, the superintendent in Anchorage cleaned out every Home Depot and Lowe’s within driving distance before even obtaining enough drain tile to meet our spec. We had no choice but to settle for a different type of drain tile that would later be modified to perform the way we needed it — and it worked beautifully.
Waiting for the specified pipe would have not only delayed the project, but also would have misaligned us with what was already a very tight budget. It is always critical to discuss such alternatives with your client and construction team. Everyone must be in agreement before such measures are taken. The moral is don’t settle for lesser performance but maintain flexibility in how you reach your end goal.
Plan for the worst, manifest the best
Build in contingencies. Not just financially but in your time and resources. The weather in Anchorage can turn for the worst much earlier than anticipated. Using as many of those 22 hours of summer daylight was key. Then preparing for continuation in the spring allowed us to finish well ahead of the tournament.
As we approached September, we knew the weather could change any day. With that in mind, we took a step back and assessed what could realistically be accomplished while redirecting resources to winterize the remainder of the course. This allowed for a seamless restart of the project when the drier spring weather arrived — which allowed us to hit our timelines before the tournament.
Communication is key
Keep everyone informed. Whether you are a public course or a private club, renovation projects always go smoother when your clientele is involved early and often. Design by committee can be dangerous, but in most cases, your golfers just want the opportunity to be heard. Their sense of involvement, along with providing updates and photos of progress, will ensure that complaints are minimal when it comes to disrupting their course.
In Anchorage, the disruption provided a sense of progress and exciting things to come for the golfers. As a result, the sense of support and pride as the tournament approached was overwhelming. The community showed up in droves to watch some of the best amateur golfers in the world. From the taxi stand at the airport to the local restaurants, most people knew about and were excited for the tournament. It takes a village. When we involve the community in the process, special things can happen.
I believe the lessons passed along here will apply to any golf course project. Some of them might seem very simple and should almost be a given. But every project has different dynamics, which can affect the process. Regardless of the project schedule and budget, it is always worth taking a step back to assess the big picture.
The seven lessons included here should always be a part of that picture.
Golf course architect Jeff Danner is a partner at Richardson | Danner and one of just three architects globally who are members of both the American Society of Golf Course Architects and the European Institute of Golf Course Architects.
Latest from Golf Course Industry
- Golf Construction Conversations: Reed Anderson
- ’Twas the Night Before Christmas (on turf)
- Twas the Night Before Christmas (the turf version audio)
- Advanced Turf Solutions and The Aquatrols Company release soil surfactant
- Heritage Golf Group acquires North Carolina courses
- Editor’s notebook: Green Start Academy 2024
- USGA focuses on inclusion, sustainability in 2024
- Greens with Envy 65: Carolina on our mind