Cultivation programs have been implemented and studied across the country. For example, the USGA Green Section sponsored research at the University of Georgia in the 1990s, and the results of that work provided Georgia-specific data for cultivation and topdressing recommendations for sand-based greens commonly known as “organic matter dilution” programs. A 2003 article published in the Green Section Record magazine summarized the details of this approach, recommending annual cultivation practices that remove 15 to 20 percent surface area and incorporate 40 to 50 ft3 sand/M, with the ultimate goal being to maintain surface rootzone organic matter at four percent or less. Aggressive organic matter dilution programs are intended to manage aeration porosity and subsequent infiltration rates, thereby allowing superintendents to more easily manage their putting greens and lessen the effects of summer environmental stresses.
Table 1. Treatment Details & Thatch / Mat Organic Matter % at end of 2008. *Within a column, values followed by the same letter are not significantly different.
Table 2. Total estimated days of disrupted putting quality in 2009 as affected by percent surface removal by various core cultivation and verticutting treatments. *Two passes with the 0.25” inside diameter (id) tines on Sept 10 resulted in undue tearing, hole overlap, and furrowing on the putting surface that served to delay recovery in treatments 2 and 5 in September; this type of tearing did not happen with treatment 2 in the spring, so recovery was faster. **Treatment 7 cultivation did not all occur on Sept 10, as verticutting after 0.25” id double-pass coring was causing undue sod lifting/damage. Verticutting was delayed until 26 days after coring, unduly lengthening recovery time to 52 days for this treatment.
Our data focus will be on measurements of percent organic matter (%OM from loss on ignition tests) in the thatch/mat layer at the end of each season as affected by the various cultivation treatments and on our estimates (from digital image analysis) of days required to achieve 99 percent recovery following cultivation. At the end of 2008, only those coring treatments that removed 14.8 to 19.6 percent (Treatments 5-6) significantly reduced %OM relative to the untreated control (Table 1). Use of smaller tines-alone (Treatment 2), verticutting-alone (Treatment 3), or combinations of the two (Treatment 4), failed to reduce %OM in 2008. At the end of 2009, all treatments, except verticutting alone, significantly decreased %OM in the thatch/mat layer relative to the control (Table 1). Coring spring and fall with 0.5 inch id tines on a tight spacing to remove approximately 9.8 percent surface area to a depth of 2 inches (Treatment 5) resulted in the least OM (3 percent) over the two years. These data imply that verticutting to a depth of 0.75 inches does not remove enough material for adequate organic matter dilution, even though this procedure removes a large amount of surface area (11.8 percent) with each pass. To track percent cover or recovery rate following cultivation treatments in 2009, digital images were taken every 7 to 14 days with a light box and analyzed with SigmaScan software. Linear regression was used to predict the number of days required for each treated plot to return to 99 percent cover or a non-disrupted putting surface (Table 2). Fastest spring recovery of 24 days was measured for Treatments 2 (small tine coring) and 3 (verticutting). Large diameter coring (Treatments 5-7) or small diameter coring and verticutting on the same day (treatment 4) required 31 to 36 days for spring recovery (Table 2). Late summer/early fall recovery data were very similar to recovery times for spring treatments. In particular, Treatment 3 (verticutting), recovered in only 21 days (Table 2), while large-diameter coring alone (Treatment 6) required only two extra days of recovery (38 days vs 36 days), relative to the spring. Fastest early September recovery of seven days was with Treatment 4, where only 2.5 percent surface removal occurred. Data interpretation for the remaining treatments (2, 5, and 7) is confounded by unforeseen irregularities in how the treatments were applied. For Treatments 2 and 5, when the second 0.25 inches id coring pass was made, surface tearing and furrowing occurred, causing a higher percent surface damage than the predicted 5 percent. We are unsure why this occurred, as new tines on a new machine were used. Our supposition is that undue rootzone wetness and an algae-weakened putting surface caused failure of this double-pass treatment. As a side-note, the summer of 2009 in Virginia was one of record cool temperatures coupled with above-average rainfall. Extra damage on these two treatments (2 and 5) appeared to extend recovery by an extra 10 days relative to spring recovery times. Interpretation of the recovery time for Treatment 7 should be tempered by the fact that verticutting could not be completed over the top of plots that received two passes of the 0.25 inch id tines. Undue sod heaving occurred, so verticutting was delayed until 26 days after coring, greatly extending recovery to 52 days. In summary, two years of data indicate what most golf course superintendents already know: “There is more than one way to skin a cat.” Various coring approaches can be mixed and matched with verticutting and consistent sand topdressing to achieve the goal of OM dilution and the accompanying benefit of exceptional putting green performance. Preliminarily, our data indicate that as little as 10 percent surface area removal via spring and fall coring may be sufficient for Virginia conditions, while 15 percent to 20 percent annual removal should almost always keep you on the safe side. While verticutting alone provides fast healing, our data indicate that it needs to be combined with at least one annual coring for adequate results.
By Erik Ervin, PH.D. and Adam Nichols |
Explore the April 2011 Issue
Check out more from this issue and find your next story to read.
Latest from Golf Course Industry
- Editor’s notebook: Green Start Academy 2024
- USGA focuses on inclusion, sustainability in 2024
- Greens with Envy 65: Carolina on our mind
- Five Iron Golf expands into Minnesota
- Global sports group 54 invests in Turfgrass
- Hawaii's Mauna Kea Golf Course announces reopening
- Georgia GCSA honors superintendent of the year
- Reel Turf Techs: Alex Tessman